Level 2: Income statement and schedules Exercise 27 of 74

Timing flags for a project

A financial modeling exercise from Modeldrill. Solve it with a live spreadsheet grid in your browser, with Fill right and Fill down, and it is checked the moment you submit.

The task

A project only earns revenue while it operates. Fill the operating flag (row 7: 1 in every year from the first operating year in B2 to the last in B3, both included, otherwise 0) and revenue (row 8: the flag times the full-year revenue in B4).

What this exercise teaches

A flag row of 1s and 0s keeps timing in one place. Every line that depends on the operating period multiplies by the flag, so moving the start date is one input change instead of a rewrite of each row.

A hint if you get stuck

The flag is an IF around AND with two tests against the locked start and end years. Revenue is then just the flag times the locked full-year amount.

Functions used: AND, IF